Computer Science building
Konemiehentie 2
CS Building (Konemiehentie 2) was completed in 1998, and its building services systems are nearing the end of their life cycle. This has been visible to users, among other things, as poor indoor conditions in the spaces.
During the summer of 2025, the building automation system will be renovated, the HVAC units will be modernized, and the cooling valves and room controllers will be replaced.
The detailed table below shows the ventilation outages, when there is no ventilation in the area in question. It is recommended that you do not work in those premises at that time, as conditions may be poor due to the lack of ventilation and cooling.
If work is required on the premises during outages, windows can be opened, but closing the windows at the end of work is very important (windows must not be left open).
Duration | Area on the map | |
---|---|---|
301TK Offices and meeting rooms | Weeks: 25-31 (16.6.-1.8.) | 301TK, red area |
302TK Class rooms T2-T6, guild spaces, rooms in the A side inner corridor | Weeks: 24-29 (9.6.-18.7.) | 302TK, green area |
303TK Restaurant, lobby, Learning Hub | Weeks: 24-30 (9.6-25.7.) | 303TK, blue area |
304TK Process hall | Weeks: 22-24 (26.5-13.6.) | 304TK, brown area |
305TK Auditorium, T1, T7, T8, TIK guild | Weeks: 26-31 (23.6.-1.8.) | 305TK, yellow area |
306TK Sodexo's kitchen, Donors Lounge | Weeks: 25-26 (16.-27.6.), Lounge 17.6.-> | 306TK, purple area |
The maps below, you can see the detailed working areas (for aaltonians only, remember to log in!).
Konemiehentie 2