Demolition work and test blasting on Metallimiehenkuja

NCC Suomi Oy will conduct exploratory excavation, drilling and blasting work, which will generate environmental noise at Metallimiehenkuja 6-8.
Lisään tänne tietoa Metallimiehenkuja 6-8:sta ja opiskelija-asuntohankkeesta.

The excavation will include pre-splitting drilling and blasting. The first test blasts will be carried out on Thursday of week 11 (March 13, 2025). The blasting times are 9:30–9:45 AM and 1:30–1:45 PM. The test blasts will define the schedule for the

Further high noise level work will continue according to the previously distributed schedule from February 3 to November 15, 2025, on weekdays from Monday to Friday between 7:00 AM and 6:00 PM, and, if necessary, every other Saturday between 9:00 AM and 5:00 PM. Regular construction work may also be carried out outside these time windows.

Pedestrians are advised to pay attention to heavy traffic near the construction site.

More information:


NCC Suomi Oy, Supervisor Jari-Pekka Valtonen, p. 010 507 51 (NCC switch)

Osa Metallimiehenkuja 6-8 puretaan

Construction site at Metallimiehenkuja started in February

The construction site causing noise and heavy traffic in Otaniemi started in February.

News
  • Updated:
  • Published:
Share
URL copied!

Read more news

Eeva Furman in a black dress and gloves standing in a field with yellow flowers and trees in the background.
Appointments Published:

‘My entire career as a marine biologist and sustainability scientist has been extremely interesting’

Professor of Practice Eeva Furman has spent most of her career conducting interdisciplinary research in sustainability sciences
A red error notice window titled 'IT Services'
Incidents, University Published:
Workshop space with tables and machines. A large red prohibition sign is superimposed over the scene.
Campus Published:

Holiday breaks and special opening hours at Arts infra

Special opening hours and exceptions at Arts infra workshops.
Otakaari 8
Campus Published:

Construction work at Otakaari 8 started

Renovation work at Otakaari 8 has started in January.