Excavation on Otaniementie to start 3rd March
 
  Blasting will be carried out 1–4 times a day. The work will last approximately until the end of March. Traffic on Otaniementie and Otakaari will be stopped during the blasts.
Currently known dates for blasting
- Tuesday 9 March, on the equal hours from 11:00 to 16:00
- Wednesday 10 March, on the equal hours from 08:00 to 16:00
- Thursday 11 March, on the equal hours from 08:00 to 16:00
- Friday 12 March, on the equal hours from 08:00 to 15:00
You can order text message notifications concerning the excavation work. Jokeri Light Rail will send out notifications approximately one hour before each blast. You can order the service by sending the message RAIDE OTANIEMI to 18200. The service is free of charge.
We work mainly between 7 am and 6 pm on weekdays. We may perform some less noisy work in the evenings between 6 and 10 pm, at weekends and on mid-week holidays.
Further information
weekdays 8–16
Worksite hotline,
°±ð¾±±ô²¹²Ô¾±±ð³¾¾±â€“O³Ù²¹²Ô¾±±ð³¾¾±
tel. +358 (0)40 862 6226
24 h
 hotline
tel. +358 (0)50 465 4969
Read more news
 
  Eight new teams onboarded the Aalto Creatives pre-incubator programme this autumn
Eight new teams onboarded the Aalto Creatives pre-incubator programme this autumn. With ideas stemming from fields such as design, gaming, music, AI and XR, the teams take their first steps towards becoming startup founders. 
  THIS ’N’ THAT Exhibition: Works from the Workshop Masters in Väre
School of Arts, Design and Architecture's Workshop Masters’ exhibition showcases the school’s diverse workshop activities and the craftsmanship of the workshop masters. 
  Campus sustainability champion: concrete actions for creating hope
The Planetary Practices Workshops series was selected as the Campus sustainability champion 2025. 
   
           
           
           
           
           
          