iCONS: Boosting construction productivity with indoor positioning

The iCONS research project by Aalto University used indoor positioning technology on construction sites, but what started out as a real-time resource reporting study morphed into a production-waste measurement exercise.
Rakennustyömaa

The concluding seminar for the iCONS (Intelligent Construction Site) project took place on 8 February 2019 in Otaniemi. In his opening presentation, Professor Olli Seppänen of Aalto University summarised the key findings of the two-year study. 'There’s a huge amount of waste and variation in construction,' he said. 'We should aim at doubling or trebling productivity, as shipbuilding has already done.'

Positioning technology provides objective data

Aalto University and the eight companies involved in the iCONS consortium used positioning and technologies related to the Internet of Things (IoT) to make the construction site intelligent. They were able to obtain real-time data of the location and movements of people, equipment, and materials.

Johannes Koponen of VISMA, the key technology provider in the project, described how the IoT was used in the project, explaining how  workers wore beacons the size of a key ring, while sticker-like devices were attached to materials and equipment. Gateways were distributed around the construction site. They monitored the position of the beacons and sent respective real-time data to the cloud for analysis. In addition, craftspeople utilised a mobile app to find items on the site. The technology was also useful for managing projects and material flows, improving workplace safety and tracking resources.

Most of the craftspeople’s time on a construction site is wasted

Analysing the iCONS data, the researchers could see tangible proof of productivity problems at the eight Finnish construction sites. Overall, craftspeople spent an average of 52% of their work hours at the workface. However, they stayed there for more than ten minutes only 34% of the time; yet ten minutes is the minimum work period that can be regarded as value-creating.

The workers had little or no control over the reasons for this inefficiency. They were either collecting equipment and materials or looking for information. Further, 50% of their time they were not where they were supposed to be according to the main contractor’s schedule. The craftspeople had to micromanage the work by themselves in order to meet their targets.

Logistics is a key to productivity improvement

Ari Viitanen, partner at Carinafour, referred to his company’s experiences in shipbuilding. He proclaimed that variation kills cost efficiency and lowers work satisfaction. 

Viitanen told how 20% of productivity variation is due to internal issues, such as differences in methods, variable skills and ease of installation. External variation has a 50% impact, and often stems from design errors, delays in preceding work, a lack of resources, poor communication, bad weather and so on. Unplanned supply of building materials is one of the key culprits. Aalto University researchers found that materials typically change location eight times within the construction site.

The key to improving construction productivity is thus to minimise variation. Together with building contractor Fira, Carinafour devised an efficient logistics process for takt production. In this process, daily installation packages are delivered, on time, from an assembly and logistics unit to the building site. They’re then tagged with beacons that help monitor the material flow and provide data for continuous process improvement.

Access to digital information is a must in lean construction

¹ó¾±°ù²¹â€™s&²Ô²ú²õ±è;Otto Alhava and Jarmo Kärkkäinen shared a building contractor’s view on lean construction and digital tools that can support it. Their case study was Capella, a 7-storey apartment building project in which Fira used takt production and digital management tools.

According to Kärkkäinen, there are three steps to the digitalisation of construction: 'Bits to the floor slab, shared apps and the flow of information from one app to another.' In practice, even the first step is a challenge. When mobile data connectivity is poor, workers must walk to the site hut to access the necessary digital information and take it back to the workface in printouts.

At Capella, Fira set up a WiFi network inside the building and used a mobile app to do weekly and daily task management and to deliver work orders. Subcontractors could also send 'roadblock' alerts to the main contractor. Furthermore, Fira shared design information from BIMs with the craftspeople. IoT sensors beamed humidity and temperature information to the cloud.

The Capella experiment paid off: the project was completed two months ahead of schedule.

Individual’s productivity is the key

'The productivity of the construction sector will not pick up until the productivity of individual workers improves,' Otto Alhava reminded. Craftspeople must have the necessary information, materials, and tools in the right place at the right time so that they can be productive.

In the last presentation, Kari Lamberg voiced the concerns of The Finnish Construction Trade Union. Recording people’s movements within the site should not be taken for granted. It must always be agreed on mutually between employers and employees.

The presentations and the lively discussion at the event indicate that the industry is ready to take concrete steps toward better productivity. It will be a joint effort, where especially the craftspeople’s voice must be heard.

Building 2030

The Building 2030 project envisions, researches and promotes a better future of construction.

Read more
Building 2030
  • Updated:
  • Published:
Share
URL copied!

Read more news

A person with short dark hair wearing a light grey polo shirt in front of a solid grey background.
Studies Published:

Chemical engineer Mikko Manninen: 'I want to see how biotechnology expertise can be applied in practice'

When Aalto University chemical engineering student Mikko Manninen chose biotechnology as his Master’s major, everything fell into place. He has found his field and is now working on his Master’s thesis at the company of his dreams.
A woman in white stands in a theatrical dressing room with violet walls, a lit vanity mirror, and hanging clothes.
Cooperation, Research & Art Published:

Hämeenlinna Art Museum’s exhibition brings artworks to life through film

Hämeenlinna Art Museum will open a new exhibition Kehyskertomuksia: 24 fps / Reframing Cinema, produced in collaboration with the Aalto University Department of Film ELO.
An eye by Matti Ahlgren.
Press releases Published:

New macular degeneration treatment the first to halt disease’s progression

Aalto University researchers have uncovered a promising way to treat the dry form of the age- related macular degeneration (AMD) in the early diagnosis phase that could potentially stop its progression. The novel treatment approach aims to strengthen the protective mechanisms of affected cells using heat, explains Professor Ari Koskelainen.
Left: Daniela da Silva Fernandes, right: Robin Welsch.
Press releases Published:

AI use makes us overestimate our cognitive performance

New research warns we shouldn’t blindly trust Large Language Models with logical reasoning –– stopping at one prompt limits ChatGPT’s usefulness more than users realise.