Jokeri Light Rail contact lines installed in March

Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
A machine fixing contact lines over tracks.

Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.

The contact line work is scheduled to last until Week 13.

Additional information

Text: Jokeri Light Rail

  • Updated:
  • Published:
Share
URL copied!

Read more news

Advertisement for the XII Unite! Dialogue conference at Aalto University, showing a night view of Helsinki waterfront.
University Published:

Save the Date: XII Unite! Dialogue at Aalto University

Aalto is pleased to host more than 300 invitees at the XII Unite! Dialogue from 6 to 9 October 2025. Registration is now open, with invitations issued to nominated attendees across the alliance.
A group of people sitting on stairs with large orange bean bags around them.
Cooperation, University Published:

Erasmus+ Staff Training Week: Transnational Joint Courses and the Exchange Student’s Path from Home to Host

Twenty-five participants from across Europe gathered at Aalto University for this year’s Erasmus+ Staff Training Week, focused on transnational joint courses and student mobility.
Näkymä Otaniemen kampuksen keskiöstä
Campus Published:

Research result: Customer satisfaction with Aalto University campus premises remains high

ACRE assesses the satisfaction of its facility tenants through a customer satisfaction survey. Read about the results of the latest survey.