Read the final report of the studies carried out within the DICTION consortium.
diction-kuvio-01

The DiCtion project investigated various ways to achieve the shared situation picture. A key challenge that we explored was that different project stakeholders have their own view of the construction schedule because they are thinking in terms of their own work. In earlier attempts to resolve this, rigid approaches have been implemented, for example by forcing everyone to follow the same breakdown of work and locations. However, this rigid breakdown does not work well for any one of the parties and results in difficulties in updating information or adapting to changes. Our goal was to allow freedom of action for each stakeholder and to be able to combine the freely generated information into one, shared, project situation picture to enable collabora- tive planning. This required research and development related to developing underlying data models, creating the rules necessary for integrating information on a construction project level, enabling freedom and collaboration in planning future work, and finally finding out in real time what has happened before.

The goal of work packages B and C was to identify a common generic data model for creating, sharing and managing workflow data (WP B) and identifying new ways of planning (WP C). The work packages turned out to be tightly interrelated, so their results are reported in one report. It was necessary to start by looking at decentralized planning and how plans are currently done on different levels, to figure out what is critical on the data model side.

Situation picture can be understood as integration between theoretical plans and actual progress on site. While the traditional process digitalizes information by human entry based on perceptions, new technology allows automated data acquisition by sensoring and computer vision and comparisons to theoretical plans. Situation picture emerges by comparing plans with reality and alerting decision makers of any deviations.

Report on Business Models for Linked Building Data

Diction – Prerequisites for digitalizing construction workflows

Overcoming the productivity problem in construction

Report on DiCtion WP D Engineer-to-order supply chains and logistics processes

Diction - Deliverable DA.2

Shared situation picture

Requirements for architecture and ontology for information sharing

  • Updated:
  • Published:
Share
URL copied!

Read more news

Abstract structure of pale rods and rough wooden planks against a light blue background
Research & Art Published:

Pressed by the devil , shaped by the future

Curly birch shines in Aalto University’s Wood Studio’s fresh perspectives at the Craft Museum of Finland’s summer exhibition.
Group in black and gold costumes tosses silver balls in bright dance studio
Research & Art Published:

When atoms begin to dance – At Aalto University, metallurgy became choreography

On the Dance Metallurgy pilot course, copper ions were given movement and a face. When a metal essential to the green transition stepped onto the dance floor, chemical phenomena that often seem intimidating opened up in an entirely new way.
Person in striped shirt leaning on white round column by teal wall, hands clasped
Appointments Published:

Emrecan Gulay started as a Data Agent at the School of Business

Aalto Open Research Network has a new member, Emrecan Gulay. Their aim is to support data management practices at the School of BIZ.
Three people hold yarn spools in front of large green textile machinery in a factory setting.
Cooperation, Research & Art, University Published:

Design at the start of the supply chain – Aalto University leads a major EU project to transform textile colouration practices

The EU Horizon-funded MELANGE project brings together design, technology and business to rethink colouration practices in the textile industry and accelerate the transition towards circular and sustainable textile systems.